Sync Hubs

Jump to Section

Central Configuration can be used to quickly synchronize individual configuration objects or entire projects between two hubs. To synchronize objects, perform the following steps.

  1. Click Project and select the Sync tab.

  2. The Source hub is the current hub you are connected to.

  3. The Target is the hub being synchronized.

  4. To sync everything to the target, select Full Project. If Full Project is disabled, use the browse to select individual objects or tagged objects. When selecting a Tag, all objects with tagged with that Tag are selected. You can then de-select any objects that you don’t wish to sync.

  5. To sync all flows as disabled, enabled the Disable Activity setting. Otherwise flows are synced with the current enabled/disabled state.

  6. Click Sync.

  7. The Complete tab shows whether synchronization succeeded for each object.

Synchronization cannot be rolled back or reverted and partial success is possible if some objects fail to synchronize.

A screenshot of a computer Description automatically generated